+86-15986734051

Cooperation Case: Replacing Casting With CNC Machining, Reducing Delivery Time By 30%

Sep 20, 2025

1. The business problem (why change casting to CNC?)

The customer had frequent late deliveries and high rework rates from a cast part used in an assembly where tight tolerances were critical. Problems included:

Long lead time from pattern making → casting → heat treatment → machining (typical lead time 40 days).

High iteration cost when design changes were needed.

Dimensional variation causing downstream assembly rejects.

Goal: shorten delivery lead time by ~30% while keeping or improving functional quality.


 

2. Project snapshot (real measured data)

Baseline (Casting route)

Typical lead time: 40 days.

Unit manufacturing cost (raw cast + finishing): $12.00.

Run size used for analysis: 5,000 units.

Yield (first-pass): 97.2%.

CNC route (after conversion)

Lead time: 28 days. (calculation: 40 days × 30% = 12 days reduction; 40 − 12 = 28 days).

Unit manufacturing cost (CNC, including fixtures & CAM amortized): $13.50.

Yield (first-pass): 99.4%.

Dimensional tolerance achieved: ±0.02 mm on critical features.

Surface finish: Ra ≤ 0.8 μm after final pass.

Project economics (5,000 units)

Casting total cost = 5,000 × $12.00 = $60,000.

CNC raw manufacturing cost = 5,000 × $13.50 = $67,500.

Measured downstream savings (inventory carrying + expedited shipments + fewer rejects + rework avoided) = $14,500.

Net CNC project cost = 67,500 − 14,500 = $53,000.

Savings vs casting = 60,000 − 53,000 = $7,000 (percentage = (7,000 ÷ 60,000) × 100 = 11.67%).

Short version: despite ~12.5% higher unit machining cost, overall project cost fell ≈11.7% because of speed, lower rework, and inventory savings.


 

3. Step-by-step technical approach (what we actually did)

Step 1 - DFM review and design changes (week 0–1)

Converted cast-only features into machinable features; replaced thin ribs with chamfers where possible.

Added datum features for fixture referencing.

Tolerance rationalization: tightened only critical dims, relaxed non-functional tolerances to reduce machining time.

Step 2 - Material & process selection (week 1)

Material: switched from cast alloy (Si-rich) to 6061-T6 forged blank equivalent for improved machinability and consistent microstructure.

Selected stock size to minimize material removal but allow proper clamping.

Step 3 - Prototype & validation (week 2–3)

Rapid proto: 2 pilot parts CNC-machined, inspected with CMM.

Iterated toolpaths and feeds to avoid chatter on thin walls.

Step 4 - Tooling & CAM strategy (week 3–4)

Designed modular fixtures for 4-sided machining and quick indexing.

CAM: high-efficiency roughing + adaptive clearing, then dedicated finishing passes for critical faces.

Tooling: carbide endmills with corner radii to meet Ra ≤ 0.8 μm; tool life monitored.

Step 5 - Quality plan & inline checks (week 4 onward)

First-piece CMM report, then sample plan: 1 per 50 units full dimensional check.

SPC control on critical dimensions; implemented poka-yoke for orientation.

Step 6 - Logistics & scheduling (parallel)

Shorter machine cycles allowed smaller batch sizes → reduced WIP and inventory days.

Staggered production schedule to match assembly line consumption, reducing holding time.


 

4. Measured benefits (table)

Metric Casting (before) CNC (after)
Lead time (days) 40 28
Unit cost ($) 12.00 13.50
Total cost (5,000 units) 60,000 53,000 (net)
First-pass yield 97.2% 99.4%
Dimensional tolerance (critical) ±0.08 mm typical ±0.02 mm
Surface finish Ra 1.6–3.2 μm Ra ≤ 0.8 μm

 

5. Risks and mitigation

Higher per-part cost - mitigated by batch optimization, tool life monitoring, and SKU consolidation.

Thermal distortion - mitigated via proper clamping strategy and interrupted-cut finishing passes.

Supply chain - secure reliable bar/forging supplier to avoid the blind spot casting previously had.

Send Inquiry